Plan around a supplier’s minimum order
Separate measured requirement from the minimum purchasable quantity.
By CalcForge ·
Method
Check the minimum and increment independently. Round the requirement up to an increment, then enforce the minimum if it is larger.
Worked example
A requirement of 0.72 m³ from a supplier with a 1 m³ minimum and 0.25 m³ increments means buying 1 m³.
What to check
Find out whether the increment is counted from zero or only above the minimum.
Use the material calculator when the product is sold by area per pack.