Plan around a supplier’s minimum order

Separate measured requirement from the minimum purchasable quantity.

By CalcForge ·

Method

Check the minimum and increment independently. Round the requirement up to an increment, then enforce the minimum if it is larger.

Worked example

A requirement of 0.72 m³ from a supplier with a 1 m³ minimum and 0.25 m³ increments means buying 1 m³.

What to check

Find out whether the increment is counted from zero or only above the minimum.

Use the material calculator when the product is sold by area per pack.

Open the material pack calculator ↗